The new Holy Family Home

Construction of the New Holy Family Home in real-time!


Facility Highlights

The new building design consists of 112,000 square feet, including significant renovations to part of the existing building to update the independent living apartments and new construction for the healthcare household and convent area.

  • Healthcare Household with 18 private rooms with bathrooms

  • Independent Living Apartments, including 20 studio and 17 one-bedroom apartments

  • A modest convent area (15 bedrooms) enabling our Sisters to truly share the Home with our Residents

  • A beautiful chapel adjacent to the main entrance for daily Mass and prayer for Residents

  • Generous community and activity spaces, including living rooms, dining rooms, activity rooms, physical therapy rooms, courtyards, and a library

  • Areas for socialization including a beauty salon, sundry and gift shop, and bistro area

  • Multiple laundry rooms on each floor for Residents’ convenience

  • Administrative offices to ensure staff remain engaged with our Residents and immersed in our mission.


Timeline

Fall 2019 – Early Spring 2022

Design Development and Site Planning

Spring 2022 - Spring 2023

Begin Phase 1: Healthcare Household and Convent

Spring 2023 - Beginning of 2024

Begin Phase II: Independent Living Apartments and Community Center

Beginning of 2024 - Summer 2024

Begin Phase III: Community Center and Chapel


Estimated Cost Breakdown by Phase

Predevelopment: $3,000,000

Phase 1: $17,750,000

Phase 2: $15,750,000

Phase 3: $8,500,000

Total Project: $45,000,000